Construction of a fire station


Purpose: To ensure fire safety of the facilities of the park.

 

Benefits for residents of Solomonovo industrial park : minimization of funds for provision of fire protection of the facilities, free-of-charge maintenance of the facilities, quick response in case of necessity, etc.

 

Social impact: construction of the object of social infrastructure to ensure fire safety in the industrial park and the surrounding areas, including Chop city and Solomonovo village. The conceptual approval of the Head Office of Ministry of Emergencies of Ukraine in the Transcarpathian region of Ukraine is received on joint implementation of the project.

The parameters of the object:

  • fire station for 4 cars, including 2 major + 2 reserve;
  • land area - 0.324 hectares;
  • built-up area of the main building - 0.055 hectares;
  • number of employees - 20 people.;
  • additional facilities - sports and training area, parking, green zone, a fire pond

Construction of the substation


Purpose: to ensure a power supply of facilities of the park.

Benefits for residents of Solomonovo industrial park: the ability to use a lot of power, minimizing the funds for electrification of the facilities, reducing of the costs on payment for reactive energy, etc.

Social impact: construction of the object of social infrastructure with the purpose of electrical supply in the industrial park and the surrounding areas. The construction of this object and its subsequent transfer on the balance of Zakarpatoblenergo will provide for an additional uninterrupted power supply of Solomonovo village territory.

The parameters of the object:

  • step-down station PS 110/35/10 kV;
  • land area - 0.4 hectares;
  • two transformers rated at 25 kVA.